CBAM verification: the route to better EU market access

In conversations with companies, I often hear CBAM verification described as primarily a check of the report.

That is not correct. CBAM verification is not a check of a single Excel sheet.

What is verified is the entire system that produced that sheet: from data collection to the final emissions calculation.

For companies that will use actual emission values for 2026, this difference has immediate practical consequences. The first publicly documented CBAM verifiers have already been accredited, and verified data will go into the first annual CBAM declaration for 2026.

What does this mean in practice for a manufacturer?

The verifier will not stop at the question:

“Is the calculation correct, and what are the emissions per tonne of product?”

The check will also cover questions that determine the reliability of the whole system: Where does this figure come from? Who took the measurement? With which meter? Which formula produced the result? Why is there no meter at a particular point? Where is the original data? How are emissions allocated between products? Who changed the data? What assumptions were made? Was the monitoring plan actually applied?

The monitoring plan: the document that links the system to the report

For some operators this will be their first encounter with the requirement for a monitoring plan. Yet it is a very important document: from it, the verifier sees how the operator obtained its information, which procedures it applied and how it carried out the calculations on which the report is based.

Challenge 1: Everything stated in the monitoring plan must be consistent with the report.

Challenge 2: Everything stated in the report must be accurate, with minimal deviation from the result of the verifier’s check.

So expect at least the following to be checked:

  1. the monitoring plan and installation boundaries;
  2. production processes and material flows;
  3. consumption of fuels, raw materials and electricity;
  4. measuring instruments, factors, calculation formulas and data sources;
  5. databases, Excel files, ERP and other IT systems;
  6. allocation between production processes and CBAM goods;
  7. relevant precursors;
  8. allocation of flows and emissions of relevant precursors;
  9. controls, corrections and documentation of changes;
  10. the original evidence behind the reported data;
  11. the emissions calculation itself and the operator’s final report.

For the first verification of an installation, also plan for a physical site visit by the verifier, except in the very specific circumstances provided for in the rules.

Special attention: precursors

I would particularly draw attention to precursors, because the reliability of their data directly affects whether you can use actual emission values.

If you use a CBAM precursor bought from another producer, it is not enough for your supplier to send you their Excel file, carbon footprint calculation or a statement of emissions.

If you want to use their actual values where the rules require verification, those data must be backed by an appropriate CBAM verification report. Otherwise, you may face the application of default values.

The materiality threshold is not an allowed error

The materiality threshold also needs to be properly understood: the 5% materiality threshold is not a permitted 5% error. We can discuss what it means and how it applies in practice in more detail when you contact us. The topic needs a fuller expert explanation than an article like this allows.

What does the verification result look like?

The good news is that negative findings during verification do not automatically mean the final outcome is unfavourable – that you have “failed”. Verification is an iterative process: errors and non-conformities that are identified can be corrected.

A much bigger problem arises when there is no adequate evidence.

The CBAM verifier does not verify only the final result of the calculation. They must obtain reasonable assurance that there is traceability from the plant, through measurement and data processing, to the figure reported to the EU importer.

Establishing that traceability is an important part of the CBAM verification preparation we do at CirEkon, by linking the monitoring plan, supporting documentation and emissions calculations.

Don’t wait for 2027. Start now.

For Serbian manufacturers that want to use actual values for 2026, my recommendation is clear:

Don’t wait until 2027 to start building your verification file. Preparation should start now. There are at least two reasons:

  1. Allow 3 months to prepare all the documentation and systems, even if you think you are already ready. The pace of preparation does not depend only on you, but also on data availability and other participants in the process.
  2. I expect a verification bottleneck after April 2027, when a large number of companies will start the process at the same time. Imagine summer traffic to the coast at a border crossing on a Friday at 5 pm – except that here the “border” is CBAM clearance for your goods.

How much will it cost you?

If you do not carry out verification, by our estimate you should count on EUR 5–10 per tonne.

This amount covers only the emissions linked to what you did in Serbia. Precursors are not included in this estimate.

For precursors we carry out a separate forecast analysis, which we will discuss in more detail another time. For now, we can say that more often than not the potential savings run to hundreds of thousands of euros a year.

The decision is yours. Start in time.